Overview
STATUS
Completed
Location
Cross City, FL
Duration
25 days
Completion Date
July 2013
Size
1,309 SF
Type of Construction
Hard Bid
About the Project
This project consisted of the interior and exterior renovations and improvements to an existing McDonald’s restaurant. This fast track project was completed in twenty-five (25) days. Work included the complete removal and replacement of the existing restrooms, as well as major improvements to the existing dining room, exterior of the building and site. Extensive coordination was required, as the restaurant remained in operation during the entire construction process.